LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0504 · BESS · Robertson County

Barton Branch IA

Barton Branch IA is a 204 MW battery storage project in Robertson County, Texas, connecting at Tap 345kV 3400 Twin Oak - 39950 TNP One. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/01/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0504
Capacity
204 MW
Fuel
BESS (BA)
Interconnecting entity
Barton Branch IA LLC
Projected COD
10/01/2026
Entered queue
02/17/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/18/2025
    FIS Approved → IA Signed
  • 06/16/2025
    FIS Requested → FIS Approved
  • 02/17/2021
    Entered the queue with 204 MW, projected COD 10/01/2026
  • 02/17/2021
    Screening → FIS Requested

Other projects at this substation