Counties / Texas
Kinney County power projects
Kinney County, Texas has 8 active power projects totalling 709 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 507 MW (71%). The largest single project is Longday Solar SLF (201 MW solar). 0 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.
Active projects
8
0.7 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
3
since Sep 2026
Changes in Kinney County
COD change
10/01/2026
Turkey Creek Solar SLF · Solar · Kinney County
Projected COD moved 10/26/2027 → 09/01/2028. Delay #1 for this project.
+10 mo
COD change
10/01/2026
Turkey Creek Battery Energy Storage System SLF · BESS · Kinney County
Projected COD moved 10/26/2027 → 09/01/2028. Delay #1 for this project.
+10 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Longday Solar SLF | Solar | 201 | Tap138 kV 8252 Brackettville - 8260 Escondido | FIS Requested | 12/15/2027 |
| Turkey Creek Solar SLF | Solar | 181 | 7425 ODLASW 138kV | FIS Requested | 09/01/2028 |
| Sugarberry Solar SLF | Solar | 125 | 78255 Pinto Creek 138 kV | FIS Requested | 12/18/2029 |
| Kinney County Energy | BESS | 101 | Tap 138kV 8252 Brackett4A - 78255 L_PINTCR8_1Y | FIS Requested | 05/15/2027 |
| Las Moras Battery | BESS | 101 | 8252 Brackett 138kV | FIS Requested | 07/01/2029 |
| Longday BESS SLF | BESS | 0 | Tap 138 kV 8252 Brackettville - 8260 Escondido | FIS Requested | 12/15/2027 |
| Turkey Creek Battery Energy Storage System SLF | BESS | 0 | 7425 ODLASW 138 kV | FIS Requested | 09/01/2028 |
| Sugarberry Storage SLF | BESS | 0 | 78255 Pinto Creek 138 kV | FIS Requested | 12/18/2029 |
| DeSpain Solar Project | Solar | 236 | Not listed | Withdrawn | n/a |
| GALVANIC BESS | BESS | 100 | 8252 Bracketville 138kV | Withdrawn | 12/30/2027 |
For residents and landowners
- What power projects are planned in Kinney County?
- ERCOT's October 2026 report lists 8 active projects in Kinney County totalling 709 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.