25INR0623 · BESS · Kinney County
Turkey Creek Battery Energy Storage System SLF
COD delayed 1×
Turkey Creek Battery Energy Storage System SLF is a 0 MW battery storage project in Kinney County, Texas, connecting at 7425 ODLASW 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/01/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0623
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- 7425 ODLASW 138 kV
- County
- Kinney County
- Interconnecting entity
- Greenray Solar Corporation
- Projected COD
- 09/01/2028
- Entered queue
- 03/29/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/26/2027 → 09/01/2028 (+10 months)
- 09/13/2024Screening → FIS Requested
- 03/29/2024Entered the queue with 0 MW, projected COD 10/26/2027
Other projects at this substation
No other projects at this substation.