25INR0502 · BESS · Kinney County
Longday BESS SLF
Longday BESS SLF is a 0 MW battery storage project in Kinney County, Texas, connecting at Tap 138 kV 8252 Brackettville - 8260 Escondido. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/15/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0502
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- County
- Kinney County
- Interconnecting entity
- Longday Solar
- Projected COD
- 12/15/2027
- Entered queue
- 07/20/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/20/2023Entered the queue with 0 MW, projected COD 12/15/2027
- 07/20/2023Screening → FIS Requested