Substation / point of interconnection ยท Kinney County
7425 ODLASW 138kV
1 active project totalling 181 MW is queued to connect at 7425 ODLASW 138kV in Kinney County, Texas, according to ERCOT's October 2026 report.
Active capacity
181 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0622 | Turkey Creek Solar SLF | Solar | 181 | FIS Requested | 09/01/2028 | 1 |