Cooke County power projects
Cooke County, Texas has 5 active power projects totalling 948 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 768 MW (81%). The largest single project is Two Forks BESS (310 MW battery storage). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
0.9 GW capacity
IA signed or later
2
40% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Cooke County
COD change
10/01/2026
-2 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Two Forks BESS | BESS | 310 | 684 SPRING 138kV | IA Signed | 08/01/2028 |
| 18-ALPHA BESS | BESS | 307 | To the 138 kV Valley View Substation, ( Bus No.691) | FIS Requested | 02/01/2028 |
| WILDWIND | Wind | 180 | tap 345kV 1730 KrumW - 2373 Anna | Sync Approved | 04/15/2026 |
| Mountain Springs BESS | BESS | 150 | 704 Mountain Springs 138 kV | FIS Approved | 04/01/2029 |
| Trojan BESS SLF | BESS | 0 | 11735 Cedar Elm Switch 345kV | FIS Requested | 07/01/2029 |
For residents and landowners
- What power projects are planned in Cooke County?
- ERCOT's October 2026 report lists 5 active projects in Cooke County totalling 948 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.