Substation / point of interconnection ยท Cooke County
To the 138 kV Valley View Substation, ( Bus No.691)
1 active project totalling 307 MW is queued to connect at To the 138 kV Valley View Substation, ( Bus No.691) in Cooke County, Texas, according to ERCOT's October 2026 report.
Active capacity
307 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0328 | 18-ALPHA BESS | BESS | 307 | FIS Requested | 02/01/2028 | 0 |