Mountain Springs BESS is a 150 MW battery storage project in Cooke County, Texas, connecting at 704 Mountain Springs 138 kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0219
Capacity
150 MW
Fuel
BESS (BA)
Interconnecting entity
Mountain Springs BESS
Projected COD
04/01/2029
Entered queue
09/21/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/05/2025
    FIS Requested → FIS Approved
  • 09/21/2023
    Entered the queue with 150 MW, projected COD 04/01/2029
  • 09/21/2023
    Screening → FIS Requested

Other projects at this substation