20INR0033 · Wind · Cooke County
WILDWIND
WILDWIND is a 180 MW wind project in Cooke County, Texas, connecting at tap 345kV 1730 KrumW - 2373 Anna. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 04/15/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0033
- Capacity
- 180 MW
- Fuel
- Wind (WT)
- Substation
- tap 345kV 1730 KrumW - 2373 Anna
- County
- Cooke County
- Interconnecting entity
- Wildcat Creek
- Projected COD
- 04/15/2026
- Entered queue
- 10/18/2017
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/10/2021Energization Approved → Sync Approved
- 12/22/2020IA Signed → Energization Approved
- 02/21/2020FIS Approved → IA Signed
- 11/25/2019FIS Requested → FIS Approved
- 06/14/2018Screening → FIS Requested
- 10/18/2017Entered the queue with 180 MW, projected COD 04/15/2026
Other projects at this substation
No other projects at this substation.