Counties / Texas
Concho County power projects
Concho County, Texas has 9 active power projects totalling 2,656 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,705 MW (64%). The largest single project is Operation Sunshine (603 MW solar). 6 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
9
2.7 GW capacity
IA signed or later
6
67% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Concho County
New
10/01/2026
Trail Ranch Solar 2 · Solar · Concho County
Entered the queue at Tap 345 kV 6444 Red Creek -7077 Amos Creek. Projected COD 12/01/2029.
+133 MW
Stage change
09/17/2026
FIS Requested
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Operation Sunshine | Solar | 603 | 7077 Amos Creek 345kV | IA Signed | 04/01/2029 |
| Operation Sunshine Storage | BESS | 410 | 7077 Amos Creek 345kV | IA Signed | 04/01/2029 |
| Paint Rock Wind | Wind | 379 | Amos Creek (7077) – Bow Wood (76006) | IA Signed | 10/01/2028 |
| Lucy Solar | Solar | 352 | Tap 345kV 7077 Amos Creek - 6444 San Angelo Red Creek and 7077 Amos Creek - 76009 Twin Buttes | IA Signed | 06/30/2027 |
| Trail Ranch Solar 1 | Solar | 302 | Tap 345KV #6444 Red Creek - #7077 AMOS Creek | FIS Requested | 12/01/2029 |
| Concho Pearl Solar | Solar | 172 | Tap 345kV 76009 Twin Buttes - 7077 Amos Creek | IA Signed | 01/09/2028 |
| Concho Pearl Storage | BESS | 162 | Tap 345kV 76009 Twin Buttes - 7077 Amos Creek | IA Signed | 01/09/2028 |
| Cherry Sage Solar 1 SLF | Solar | 142 | (#60423) TREADWELL 138kV. | FIS Requested | 02/23/2029 |
| Trail Ranch Solar 2 | Solar | 133 | Tap 345 kV 6444 Red Creek -7077 Amos Creek | FIS Requested | 12/01/2029 |
| Old Sorrell Energy Storage | BESS | 43 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Concho County?
- ERCOT's October 2026 report lists 9 active projects in Concho County totalling 2,656 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.