ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0174 · Solar · Concho County

Concho Pearl Solar

Concho Pearl Solar is a 172 MW solar project in Concho County, Texas, connecting at Tap 345kV 76009 Twin Buttes - 7077 Amos Creek. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/09/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0174
Capacity
172 MW
Fuel
Solar (PV)
Interconnecting entity
Concho Pearl Solar, LLC
Projected COD
01/09/2028
Entered queue
11/30/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/22/2024
    FIS Requested → IA Signed
  • 11/30/2022
    Entered the queue with 172 MW, projected COD 01/09/2028
  • 11/30/2022
    Screening → FIS Requested

Other projects at this substation

Concho Pearl StorageBESS162 MWIA Signed