29INR0139 · Solar · Concho County
Trail Ranch Solar 1
Trail Ranch Solar 1 is a 302 MW solar project in Concho County, Texas, connecting at Tap 345KV #6444 Red Creek - #7077 AMOS Creek. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0139
- Capacity
- 302 MW
- Fuel
- Solar (PV)
- County
- Concho County
- Interconnecting entity
- Aurora Solar LLC
- Projected COD
- 12/01/2029
- Entered queue
- 11/18/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/16/2026Screening → FIS Requested
- 11/18/2025Entered the queue with 302 MW, projected COD 12/01/2029