ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0255 · Solar · Concho County

Operation Sunshine

Operation Sunshine is a 603 MW solar project in Concho County, Texas, connecting at 7077 Amos Creek 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0255
Capacity
603 MW
Fuel
Solar (PV)
Interconnecting entity
Duck Creek Solar, LLC
Projected COD
04/01/2029
Entered queue
09/27/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/27/2025
    FIS Requested → IA Signed
  • 09/27/2023
    Entered the queue with 603 MW, projected COD 04/01/2029
  • 09/27/2023
    Screening → FIS Requested

Other projects at this substation

Operation Sunshine StorageBESS410 MWIA Signed