Childress County power projects

Childress County, Texas has 3 active power projects totalling 270 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 170 MW (63%). The largest single project is Fagus Solar Park 3 SLF (170 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
3
0.3 GW capacity
IA signed or later
1
33% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
2
since Sep 2026

Changes in Childress County

Withdrawn
Unconfirmed
10/01/2026
Fagus Solar Park 2 SLF · Solar · Childress County
Missing from the latest report, not yet marked withdrawn by ERCOT. Still queued at 60501 Tesla 345 kV: 170 MW.
−167 MW
Withdrawn
Unconfirmed
10/01/2026
Fagus Solar Park 1 SLF · Solar · Childress County
Missing from the latest report, not yet marked withdrawn by ERCOT. Still queued at 60501 Tesla 345kV: 100 MW.
−166 MW

All projects

ProjectFuelMWSubstationStageCOD
Fagus Solar Park 3 SLFSolar17060501 Tesla 345 kVIA Signed06/28/2027
Independence Trail StorageBESS10060501 Tesla 345kVFIS Requested01/01/2028
Fagus Storage SLFBESS060501 Tesla 345kVFIS Requested09/01/2026
Fagus Solar Park 2 SLFSolar16760501 Tesla 345 kVWithdrawn05/20/2026
Fagus Solar Park 1 SLFSolar16660501 Tesla 345kVWithdrawn05/20/2026

For residents and landowners

What power projects are planned in Childress County?
ERCOT's October 2026 report lists 3 active projects in Childress County totalling 270 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.