LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
21INR0455 · BESS · Childress County

Independence Trail Storage

Independence Trail Storage is a 100 MW battery storage project in Childress County, Texas, connecting at 60501 Tesla 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0455
Capacity
100 MW
Fuel
BESS (BA)
Interconnecting entity
KCE TX 16, LLC
Projected COD
01/01/2028
Entered queue
10/22/2019
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/22/2019
    Entered the queue with 100 MW, projected COD 01/01/2028
  • 10/22/2019
    Screening → FIS Requested

Other projects at this substation

Fagus Solar Park 1 SLFSolar166 MWWithdrawn
Fagus Storage SLFBESS0 MWFIS Requested