20INR0091 · Solar · Childress County
Fagus Solar Park 1 SLF
Withdrawn
Fagus Solar Park 1 SLF is a 166 MW solar project in Childress County, Texas, connecting at 60501 Tesla 345kV. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0091
- Capacity
- 166 MW
- Fuel
- Solar (PV)
- Substation
- 60501 Tesla 345kV
- County
- Childress County
- Interconnecting entity
- Excel Advantage Services, LLC dba Misae Solar Park II
- Projected COD
- 05/20/2026
- Entered queue
- 05/15/2018
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Listed as withdrawn UNCONFIRMED
- 08/04/2025Energization Approved → Sync Approved
- 05/29/2025IA Signed → Energization Approved
- 02/27/2024FIS Requested → FIS Approved
- 02/21/2019FIS Approved → IA Signed
- 05/15/2018Entered the queue with 166 MW, projected COD 05/20/2026
- 05/15/2018Screening → FIS Requested
Other projects at this substation
| Independence Trail Storage | BESS | 100 MW | FIS Requested |
| Fagus Storage SLF | BESS | 0 MW | FIS Requested |