ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0515 · BESS · Childress County

Fagus Storage SLF

COD date passed

Fagus Storage SLF is a 0 MW battery storage project in Childress County, Texas, connecting at 60501 Tesla 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/01/2026. Its projected COD of 09/01/2026 has already passed without ERCOT approval to synchronize, so the date is likely to move.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0515
Capacity
0 MW
Fuel
BESS (BA)
Interconnecting entity
Greenalia Energy Storage MISAE II LLC
Projected COD
09/01/2026
Entered queue
09/22/2023
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/22/2023
    Entered the queue with 0 MW, projected COD 09/01/2026
  • 09/22/2023
    Screening → FIS Requested

Other projects at this substation

Fagus Solar Park 1 SLFSolar166 MWWithdrawn
Independence Trail StorageBESS100 MWFIS Requested