LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Caldwell County power projects

Caldwell County, Texas has 16 active power projects totalling 4,518 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 3,505 MW (78%). The largest single project is Caldwell County Energy Center (1,500 MW natural gas). 3 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
16
4.5 GW capacity
IA signed or later
3
19% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Caldwell County

COD change
10/01/2026
SCHNEIDER COMBINED CYCLE · Gas · Caldwell County
Projected COD moved 04/13/2032 → 05/10/2033. Delay #1 for this project.
+13 mo
COD change
10/01/2026
Big Watt Power Austin-1 · Gas · Caldwell County
Projected COD moved 11/01/2028 → 11/15/2028. Delay #1 for this project.
0 mo
COD change
10/01/2026
SCHNEIDER GAS RICE · Gas · Caldwell County
Projected COD moved 12/17/2030 → 12/14/2032. Delay #1 for this project.
+24 mo
COD change
10/01/2026
SCHNEIDER GAS RICE PHASE 2 · Gas · Caldwell County
Projected COD moved 12/17/2030 → 12/14/2032. Delay #1 for this project.
+24 mo

All projects

ProjectFuelMWSubstationStageCOD
Caldwell County Energy CenterGas1,500#7051 Misty Substation 345kVFIS Requested04/30/2030
SCHNEIDER COMBINED CYCLEGas880Double Tap 345kV #7042 Zorn - #7040 Austrop and #7042 Zorn - #9074 Lytton SpringsIA Signed05/10/2033
Bobcat Generating StationGas450Between (7042) ZORN & (9074) LYTTON SPRINGS Substations on ONCOR 345kV.FIS Requested11/01/2029
Big Watt Power Austin-1Gas449Tapping the 345 kV Double circuit Line: Zorn (Bus# 7042) - Lytton Springs (Bus# 9074) and Zorn (Bus# 7042) - Austrop (Bus# 7040).FIS Requested11/15/2028
Elbus BESSBESS2019075 Lytton 138kVFIS Requested06/01/2028
Metro BESSBESS201138 kV LYTTON8 (9075)FIS Requested12/07/2030
Demeter Storage 2BESS138Tap 138kV 7224 LULING - 7216 LOCKHARTFIS Requested06/01/2029
SCHNEIDER GAS RICEGas113Double Tap 345kV #7042 Zorn - #7040 Austrop and #7042 Zorn - #9074 Lytton SpringsIA Signed12/14/2032
SCHNEIDER GAS RICE PHASE 2Gas113Double Tap 345kV #7042 Zorn - #7040 Austrop and #7042 Zorn - #9074 Lytton SpringsIA Signed12/14/2032
Ardesia StorageBESS100Tap 138kV 7325 Mendoza - 7216 LockhartFIS Requested03/29/2030
Demeter SolarSolar88Tap 138kV 7224 LULING - 7216 LOCKHARTFIS Requested06/01/2029
Lytton Springs BESSBESS76Lytton Springs (#9074) – Fayette Plant (#7055) 345 kV LineFIS Requested12/01/2028
Demeter StorageBESS65Tap 138kV 7224 LULING - 7216 LOCKHARTFIS Requested06/01/2029
Lytton Springs SolarSolar55Lytton Springs (#9074) – Fayette Plant (#7055) 345 kV LineFIS Requested12/01/2028
Volunteer StorageBESS517216 Lockhart 138kVFIS Requested02/29/2028
TAIN SOLARSolar38tap 138kV 7216 Lockhart - 7224 Luling CityFIS Requested10/27/2027
Exodus BESSBESS201Tap 345kV 7040 Austrop – 7042 ZornWithdrawn12/01/2027

For residents and landowners

What power projects are planned in Caldwell County?
ERCOT's October 2026 report lists 16 active projects in Caldwell County totalling 4,518 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.