Counties / Texas
Caldwell County power projects
Caldwell County, Texas has 16 active power projects totalling 4,518 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 3,505 MW (78%). The largest single project is Caldwell County Energy Center (1,500 MW natural gas). 3 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
16
4.5 GW capacity
IA signed or later
3
19% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
4
since Sep 2026
Changes in Caldwell County
COD change
10/01/2026
SCHNEIDER COMBINED CYCLE · Gas · Caldwell County
Projected COD moved 04/13/2032 → 05/10/2033. Delay #1 for this project.
+13 mo
COD change
10/01/2026
Big Watt Power Austin-1 · Gas · Caldwell County
Projected COD moved 11/01/2028 → 11/15/2028. Delay #1 for this project.
0 mo
COD change
10/01/2026
SCHNEIDER GAS RICE · Gas · Caldwell County
Projected COD moved 12/17/2030 → 12/14/2032. Delay #1 for this project.
+24 mo
COD change
10/01/2026
SCHNEIDER GAS RICE PHASE 2 · Gas · Caldwell County
Projected COD moved 12/17/2030 → 12/14/2032. Delay #1 for this project.
+24 mo
All projects
For residents and landowners
- What power projects are planned in Caldwell County?
- ERCOT's October 2026 report lists 16 active projects in Caldwell County totalling 4,518 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.