LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0478 · BESS · Caldwell County

Metro BESS

Metro BESS is a 201 MW battery storage project in Caldwell County, Texas, connecting at 138 kV LYTTON8 (9075). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/07/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0478
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Metro BESS LLC
Projected COD
12/07/2030
Entered queue
02/24/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/24/2025
    Entered the queue with 201 MW, projected COD 12/07/2030
  • 02/24/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.