30INR0031 · Gas · Caldwell County

Caldwell County Energy Center

Caldwell County Energy Center is a 1,500 MW natural gas project in Caldwell County, Texas, connecting at #7051 Misty Substation 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/30/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0031
Capacity
1,500 MW
Fuel
Gas (CC)
Interconnecting entity
Caldwell County Energy Center, LLC
Projected COD
04/30/2030
Entered queue
02/03/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/29/2025
    Screening → FIS Requested
  • 02/03/2025
    Entered the queue with 1,500 MW, projected COD 04/30/2030

Other projects at this substation

No other projects at this substation.