ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0176 · Gas · Caldwell County

SCHNEIDER GAS RICE

COD delayed 1×

SCHNEIDER GAS RICE is a 113 MW natural gas project in Caldwell County, Texas, connecting at Double Tap 345kV #7042 Zorn - #7040 Austrop and #7042 Zorn - #9074 Lytton Springs. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/14/2032. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0176
Capacity
113 MW
Fuel
Gas (IC)
Interconnecting entity
LCRA
Projected COD
12/14/2032
Entered queue
07/25/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/17/2030 → 12/14/2032 (+24 months)
  • 12/19/2025
    FIS Requested → IA Signed
  • 07/25/2025
    Entered the queue with 113 MW, projected COD 12/17/2030
  • 07/25/2025
    Screening → FIS Requested

Other projects at this substation

SCHNEIDER COMBINED CYCLEGas880 MWIA Signed
SCHNEIDER GAS RICE PHASE 2Gas113 MWIA Signed