Substation / point of interconnection ยท Starr County
Tap 345kV 80355 Del Sol - 80227 Rapido
4 active projects totalling 854 MW are queued to connect at Tap 345kV 80355 Del Sol - 80227 Rapido in Starr County, Texas, according to ERCOT's October 2026 report.
Active capacity
854 MW
queued at this substation
Active projects
4
4 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0223 | Mandolin Solar II SLF | Solar | 304 | FIS Requested | 06/15/2029 | 0 |
| 26INR0527 | Mandolin Solar SLF | Solar | 300 | FIS Requested | 06/15/2029 | 0 |
| 29INR0224 | Mandolin Solar III SLF | Solar | 250 | FIS Requested | 06/15/2029 | 0 |
| 26INR0528 | Mandolin Storage SLF | BESS | 0 | FIS Requested | 06/15/2029 | 0 |