29INR0223 · Solar · Starr County
Mandolin Solar II SLF
Mandolin Solar II SLF is a 304 MW solar project in Starr County, Texas, connecting at Tap 345kV 80355 Del Sol - 80227 Rapido. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/15/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0223
- Capacity
- 304 MW
- Fuel
- Solar (PV)
- Substation
- Tap 345kV 80355 Del Sol - 80227 Rapido
- County
- Starr County
- Interconnecting entity
- Mandolin Energy Center II, LLC
- Projected COD
- 06/15/2029
- Entered queue
- 06/17/2026
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/17/2026Entered the queue with 304 MW, projected COD 06/15/2029
- 06/17/2026Screening → FIS Requested
Other projects at this substation
| Mandolin Solar SLF | Solar | 300 MW | FIS Requested |
| Mandolin Storage SLF | BESS | 0 MW | FIS Requested |
| Mandolin Solar III SLF | Solar | 250 MW | FIS Requested |