LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0224 · Solar · Starr County

Mandolin Solar III SLF

Mandolin Solar III SLF is a 250 MW solar project in Starr County, Texas, connecting at Tap 345kV 80355 Del Sol - 80227 Rapido. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/15/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0224
Capacity
250 MW
Fuel
Solar (PV)
Interconnecting entity
Mandolin Energy Center I, LLC
Projected COD
06/15/2029
Entered queue
08/25/2026
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Entered the queue with 250 MW, projected COD 06/15/2029
  • 08/25/2026
    Screening → FIS Requested

Other projects at this substation

Mandolin Solar SLFSolar300 MWFIS Requested
Mandolin Storage SLFBESS0 MWFIS Requested
Mandolin Solar II SLFSolar304 MWFIS Requested