Mandolin Solar SLF is a 300 MW solar project in Starr County, Texas, connecting at Tap 345kV 80355 Del Sol - 80227 Rapido. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/15/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0527
Capacity
300 MW
Fuel
Solar (PV)
Interconnecting entity
Mandolin Energy Center I, LLC
Projected COD
06/15/2029
Entered queue
06/24/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/24/2024
    Entered the queue with 300 MW, projected COD 06/15/2029
  • 06/24/2024
    Screening → FIS Requested