Young County power projects
Young County, Texas has 8 active power projects totalling 2,177 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 1,171 MW (54%). The largest single project is Miller Bend Energy BESS (548 MW battery storage). 1 project has signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.
Active projects
8
2.2 GW capacity
IA signed or later
1
12% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Young County
COD change
10/01/2026
Trinity Hills Wind repower · Wind · Young County
Projected COD moved 08/29/2026 → 12/31/2026. Delay #1 for this project.
+4 mo
All projects
For residents and landowners
- What power projects are planned in Young County?
- ERCOT's October 2026 report lists 8 active projects in Young County totalling 2,177 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.