LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0306 · Solar · Young County

Red Top Solar I

Red Top Solar I is a 201 MW solar project in Young County, Texas, connecting at Tap 138kV 1431 Graham SES - Short Grass 11525. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/20/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0306
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Cat Red Top Solar, LLC
Projected COD
04/20/2029
Entered queue
01/17/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/07/2026
    FIS Requested → FIS Approved
  • 10/12/2023
    Screening → FIS Requested
  • 01/17/2023
    Entered the queue with 201 MW, projected COD 04/20/2029

Other projects at this substation

No other projects at this substation.