ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0172 · BESS · Young County

Sweetheart BESS

Sweetheart BESS is a 310 MW battery storage project in Young County, Texas, connecting at Tap 345kV #1430 GRAHAM SES - # 17002 GARVEY ROAD SWITCH. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0172
Capacity
310 MW
Fuel
BESS (BA)
Interconnecting entity
Sweetheart Energy, LLC
Projected COD
12/01/2029
Entered queue
08/11/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/11/2025
    Entered the queue with 310 MW, projected COD 12/01/2029
  • 08/11/2025
    Screening → FIS Requested

Other projects at this substation

Sweetheart SolarSolar301 MWFIS Requested