Uvalde County power projects
Uvalde County, Texas has 3 active power projects totalling 223 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 221 MW (99%). The largest single project is Nightfall Solar (181 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 8 projects in the county are listed as withdrawn or cancelled.
Active projects
3
0.2 GW capacity
IA signed or later
1
33% of active projects
Withdrawn or cancelled
8
listed by ERCOT
Changes tracked
7
since Sep 2026
Changes in Uvalde County
Stage change
09/22/2026
Energization Approved
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Nightfall Solar | Solar | 181 | 138 kV Tap 8707 Dryfrio - 8234 Uvalde (new 138 kV Meil station) | Energization Approved | 12/31/2026 |
| Ashra Solar SLF | Solar | 40 | Tap 69kV bus#5823 UVALDE Switch (UVALDESW9) to bus#5820 UVALDE SUB (UVALDESUB9) | FIS Requested | 06/14/2028 |
| Ashra Storage SLF | BESS | 2 | Tap 69kV 5823 UVALDE Switch - 5820 UVALDE SUB | FIS Requested | 06/14/2028 |
| Photo Solar 2 | Solar | 300 | 5885 Downie 138kV | Withdrawn | 05/31/2028 |
| PHOTO BESS 2 | BESS | 150 | 5885 Downie 138kV | Withdrawn | 09/01/2027 |
| Photo Solar 1 | Solar | 150 | 5885 Downie 138kV | Withdrawn | 05/31/2028 |
| SUNSETTER BESS | BESS | 100 | 5885 Downie 138kV | Withdrawn | 11/30/2027 |
| Photo BESS 3 | BESS | 100 | 5885 Downie Substation 138kV | Withdrawn | 09/01/2027 |
| PHOTO BESS 1 | BESS | 75 | 5885 Downie 138kV | Withdrawn | 09/01/2027 |
| Fluorite Solar | Solar | 25 | Not listed | Withdrawn | n/a |
| Basalt Solar | Solar | 20 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Uvalde County?
- ERCOT's October 2026 report lists 3 active projects in Uvalde County totalling 223 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.