Substation / point of interconnection ยท Uvalde County
138 kV Tap 8707 Dryfrio - 8234 Uvalde (new 138 kV Meil station)
1 active project totalling 181 MW is queued to connect at 138 kV Tap 8707 Dryfrio - 8234 Uvalde (new 138 kV Meil station) in Uvalde County, Texas, according to ERCOT's October 2026 report.
Active capacity
181 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 21INR0334 | Nightfall Solar | Solar | 181 | Energization Approved | 12/31/2026 | 0 |