Photo BESS 3 is a 100 MW battery storage project in Uvalde County, Texas, connecting at 5885 Downie Substation 138kV. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0380
Capacity
100 MW
Fuel
BESS (BA)
Interconnecting entity
CED Development Inc.
Projected COD
09/01/2027
Entered queue
07/25/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/14/2026
    Listed as cancelled
  • 07/26/2022
    Screening → FIS Requested
  • 07/25/2022
    Entered the queue with 100 MW, projected COD 09/01/2027