Limestone County power projects

Limestone County, Texas has 9 active power projects totalling 1,063 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 857 MW (81%). The largest single project is Varadero Solar (206 MW solar). 4 projects have signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.

Active projects
9
1.1 GW capacity
IA signed or later
4
44% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
2
since Sep 2026

Changes in Limestone County

COD change
10/01/2026
Naduah Solar · Solar · Limestone County
Projected COD moved 10/15/2027 → 04/15/2028. Delay #1 for this project.
+6 mo
Stage change
09/17/2026
Bonham Storage SLF · BESS · Limestone County
Moved from FIS Requested to FIS Approved.
FIS Approved

All projects

ProjectFuelMWSubstationStageCOD
Varadero SolarSolar206#68092 Liberty Station 345kVIA Signed04/01/2029
Fewell SolarSolar204Tap 138kV 3597 Groesbeck - 3634 Groesbeck MainIA Signed05/15/2028
Leighton SolarSolar18198 Fernleaf 138 kVIA Signed12/06/2027
Bonham Solar SLFSolar138TAP 138 kV MEXIA_2_1_8 3632 - GROES_SE1_8 3634IA Signed04/06/2027
Bonham Storage SLFBESS105Tap 138kV 3632 Mexia_Main - 3634 Groesbeck_MainFIS Approved07/01/2027
Naduah SolarSolar78Tap 69kV Ben Hur (99) - Prairie Hill (107)FIS Requested04/15/2028
Findley BESSBESS52Tap 69kV #107 Prairie Hill - #99 Ben HurFIS Approved01/01/2028
Findley SolarSolar50Tap 69kV #107 Prairie Hill - #99 Ben HurFIS Requested01/01/2028
Chariot StorageBESS50tap 69kV 99 Ben Hur - 107 Prairie HillFIS Requested02/29/2028
Tehuacana WindWind600Not listedWithdrawnn/a
Fiji SolarSolar203Not listedWithdrawnn/a
Diver Energy Storage SLFBESS0Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Limestone County?
ERCOT's October 2026 report lists 9 active projects in Limestone County totalling 1,063 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.