LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Limestone County

Tap 138kV 3597 Groesbeck - 3634 Groesbeck Main

1 active project totalling 204 MW is queued to connect at Tap 138kV 3597 Groesbeck - 3634 Groesbeck Main in Limestone County, Texas, according to ERCOT's October 2026 report.

Active capacity
204 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0367Fewell SolarSolar204IA Signed05/15/20280