LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0127 · Solar · Limestone County

Naduah Solar

COD delayed 1×

Naduah Solar is a 78 MW solar project in Limestone County, Texas, connecting at Tap 69kV Ben Hur (99) - Prairie Hill (107). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/15/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0127
Capacity
78 MW
Fuel
Solar (PV)
Interconnecting entity
Gransolar Texas Fifteen, LLC
Projected COD
04/15/2028
Entered queue
09/27/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/15/2027 → 04/15/2028 (+6 months)
  • 06/06/2022
    Screening → FIS Requested
  • 09/27/2021
    Entered the queue with 78 MW, projected COD 10/15/2027

Other projects at this substation