ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Kenedy County power projects

Kenedy County, Texas has 4 active power projects totalling 1,311 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 609 MW (46%). The largest single project is Tall Saddle Wind (523 MW wind). 0 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
4
1.3 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
2
since Sep 2026

Changes in Kenedy County

Stage change
09/29/2026
Green Ocelot Solar · Solar · Kenedy County
Moved from FIS Requested to FIS Approved.
FIS Approved
Stage change
09/29/2026
Green Ocelot Storage · BESS · Kenedy County
Moved from FIS Requested to FIS Approved.
FIS Approved

All projects

ProjectFuelMWSubstationStageCOD
Tall Saddle WindWind52380076 AJO SUBSTATION 345kVFIS Requested10/15/2029
Green Ocelot SolarSolar357Tap 345kV 80076 Ajo - 8601 CebollaFIS Approved11/17/2028
Tall Saddle SolarSolar25280076 AJO SUBSTATION 345kVFIS Requested10/15/2029
Green Ocelot StorageBESS178Tap 345kV 80076 Ajo 80076 - 8601 CebollaFIS Approved11/17/2028
Gulf Wind 2Wind226Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Kenedy County?
ERCOT's October 2026 report lists 4 active projects in Kenedy County totalling 1,311 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.