28INR0180 · Solar · Kenedy County
Green Ocelot Solar
Green Ocelot Solar is a 357 MW solar project in Kenedy County, Texas, connecting at Tap 345kV 80076 Ajo - 8601 Cebolla. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 11/17/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0180
- Capacity
- 357 MW
- Fuel
- Solar (PV)
- Substation
- Tap 345kV 80076 Ajo - 8601 Cebolla
- County
- Kenedy County
- Interconnecting entity
- Ocelot Solar LLC
- Projected COD
- 11/17/2028
- Entered queue
- 01/28/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/29/2026FIS Requested → FIS Approved
- 01/28/2025Entered the queue with 357 MW, projected COD 11/17/2028
- 01/28/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.