27INR0309 · Solar · Kenedy County
Tall Saddle Solar
Tall Saddle Solar is a 252 MW solar project in Kenedy County, Texas, connecting at 80076 AJO SUBSTATION 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/15/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0309
- Capacity
- 252 MW
- Fuel
- Solar (PV)
- Substation
- 80076 AJO SUBSTATION 345kV
- County
- Kenedy County
- Interconnecting entity
- Tall Saddle Solar, LLC
- Projected COD
- 10/15/2029
- Entered queue
- 07/01/2024
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/25/2025Screening → FIS Requested
- 07/01/2024Entered the queue with 252 MW, projected COD 10/15/2029
Other projects at this substation
| Tall Saddle Wind | Wind | 523 MW | FIS Requested |