Jackson County power projects

Jackson County, Texas has 6 active power projects totalling 830 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 426 MW (51%). The largest single project is New Hickory Solar (209 MW solar). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
6
0.8 GW capacity
IA signed or later
3
50% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026

Changes in Jackson County

Stage change
09/15/2026
New Hickory Solar · Solar · Jackson County
Moved from Energization Approved to Sync Approved.
Sync Approved

All projects

ProjectFuelMWSubstationStageCOD
New Hickory SolarSolar209OLD_HCKRY_5 bus 5323 345 kVSync Approved12/29/2026
Dios BESSBESS2018117 GANADO138kVIA Signed12/31/2027
Sayle Solar SLFSolar122Tap 69kV #5522 Edna - #5518 El Toro SWFIS Requested05/31/2028
Sayle Storage SLFBESS122Tap 69kV #5522 Edna - #5518 El Toro SWFIS Requested05/31/2028
Third Coast BESSBESS1038125 Lolita substation 138kVIA Signed12/15/2028
Texas Sun SolarSolar72Cordele Substation ; Bus no. 5524FIS Requested12/18/2027

For residents and landowners

What power projects are planned in Jackson County?
ERCOT's October 2026 report lists 6 active projects in Jackson County totalling 830 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.