Jackson County power projects
Jackson County, Texas has 6 active power projects totalling 830 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 426 MW (51%). The largest single project is New Hickory Solar (209 MW solar). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
6
0.8 GW capacity
IA signed or later
3
50% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Jackson County
Stage change
09/15/2026
Sync Approved
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| New Hickory Solar | Solar | 209 | OLD_HCKRY_5 bus 5323 345 kV | Sync Approved | 12/29/2026 |
| Dios BESS | BESS | 201 | 8117 GANADO138kV | IA Signed | 12/31/2027 |
| Sayle Solar SLF | Solar | 122 | Tap 69kV #5522 Edna - #5518 El Toro SW | FIS Requested | 05/31/2028 |
| Sayle Storage SLF | BESS | 122 | Tap 69kV #5522 Edna - #5518 El Toro SW | FIS Requested | 05/31/2028 |
| Third Coast BESS | BESS | 103 | 8125 Lolita substation 138kV | IA Signed | 12/15/2028 |
| Texas Sun Solar | Solar | 72 | Cordele Substation ; Bus no. 5524 | FIS Requested | 12/18/2027 |
For residents and landowners
- What power projects are planned in Jackson County?
- ERCOT's October 2026 report lists 6 active projects in Jackson County totalling 830 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.