LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0441 · BESS · Jackson County

Dios BESS

Dios BESS is a 201 MW battery storage project in Jackson County, Texas, connecting at 8117 GANADO138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0441
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Dios BESS, LLC
Projected COD
12/31/2027
Entered queue
05/08/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/02/2025
    FIS Requested → FIS Approved
  • 04/03/2025
    FIS Approved → IA Signed
  • 05/08/2023
    Entered the queue with 201 MW, projected COD 12/31/2027
  • 05/08/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.