ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Jackson County

Cordele Substation ; Bus no. 5524

1 active project totalling 72 MW is queued to connect at Cordele Substation ; Bus no. 5524 in Jackson County, Texas, according to ERCOT's October 2026 report.

Active capacity
72 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
n/a
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
27INR0554Texas Sun SolarSolar72FIS Requested12/18/20270