ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Grimes County power projects

Grimes County, Texas has 18 active power projects totalling 5,140 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 2,186 MW (43%). The largest single project is Central Power Station (750 MW natural gas). 7 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
18
5.1 GW capacity
IA signed or later
7
39% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Grimes County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Central Power StationGas750967 Gibbons Creek 345kVFIS Requested05/01/2027
Tyler Rose Power Plant 1Gas597Tap 345 kV Circuit 18 (#44920) Mission - (#967) Gibbons CreekFIS Requested07/01/2029
Diamante BESSBESS51440600 ROANS__POI_5 345kVFIS Approved11/01/2028
Millsing BESSBESS50244645 CNP Singleton 345kVFIS Approved10/15/2028
Smith Lake Solar DCSolar402TAP 345 KV 44645 SINGLETON - 44900 ZENITH Ckt #99IA Signed12/29/2028
Tyler Rose Power Plant 2Gas398Tap 345 kV Circuit 18 (#44920) Mission - (#967) Gibbons CreekFIS Requested12/01/2029
Treehouse SolarSolar282Tap the 345 kV Jewett (#3390) - Singleton (#44645) lineFIS Requested11/13/2028
Hill Valley BESSBESS246345 kV Singleton (#44645)IA Signed07/15/2028
Misty Hollow BESSBESS246345 kV Singleton (#44645)IA Signed07/15/2028
Treehouse StorageBESS209Tap the 345 kV Jewett (#3390) - Singleton (#44645) line, ONCORFIS Requested11/13/2028
Eagle Claw Energy CenterBESS205Singleton (Bus #44645) - Zenith (Bus #44900) Circuit #99 345 kVIA Signed03/31/2028
Vaughn Energy StorageBESS20113 Keith 138kVFIS Approved12/31/2027
GRIMES SOLARSolar15340600 Roans Prairie 345kVFIS Requested02/15/2026
Blue Jay SolarSolar1414 Iola 138kVSync Approved09/30/2025
Scrap Iron SolarSolar111Tap 138kV (#9) Bedias - (#25) North ZulchFIS Requested09/01/2028
Blue Jay Solar IISolar694 Iola 138kVSync Approved10/31/2025
Smith Lake Storage DCBESS65Tap 345kV 44645 Singleton - 44900 Zenith Ckt #99IA Signed12/28/2028
Turin TxHSR TPSS HN-6Other508 Crutchfield 138kVFIS Requested07/15/2028

For residents and landowners

What power projects are planned in Grimes County?
ERCOT's October 2026 report lists 18 active projects in Grimes County totalling 5,140 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.