25INR0045 · BESS · Grimes County
Smith Lake Storage DC
Smith Lake Storage DC is a 65 MW battery storage project in Grimes County, Texas, connecting at Tap 345kV 44645 Singleton - 44900 Zenith Ckt #99. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/28/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0045
- Capacity
- 65 MW
- Fuel
- BESS (BA)
- County
- Grimes County
- Interconnecting entity
- Smith Lake Solar
- Projected COD
- 12/28/2028
- Entered queue
- 03/07/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/30/2025FIS Requested → IA Signed
- 11/02/2022Screening → FIS Requested
- 03/07/2022Entered the queue with 65 MW, projected COD 12/28/2028
Other projects at this substation
No other projects at this substation.