26INR0004 · Solar · Grimes County
GRIMES SOLAR
COD date passed
GRIMES SOLAR is a 153 MW solar project in Grimes County, Texas, connecting at 40600 Roans Prairie 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/15/2026. Its projected COD of 02/15/2026 has already passed without ERCOT approval to synchronize, so the date is likely to move.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0004
- Capacity
- 153 MW
- Fuel
- Solar (PV)
- Substation
- 40600 Roans Prairie 345kV
- County
- Grimes County
- Interconnecting entity
- CG Grimes County LLC
- Projected COD
- 02/15/2026
- Entered queue
- 03/07/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/07/2022Entered the queue with 153 MW, projected COD 02/15/2026
- 03/07/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.