GRIMES SOLAR is a 153 MW solar project in Grimes County, Texas, connecting at 40600 Roans Prairie 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/15/2026. Its projected COD of 02/15/2026 has already passed without ERCOT approval to synchronize, so the date is likely to move.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0004
Capacity
153 MW
Fuel
Solar (PV)
Interconnecting entity
CG Grimes County LLC
Projected COD
02/15/2026
Entered queue
03/07/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/07/2022
    Entered the queue with 153 MW, projected COD 02/15/2026
  • 03/07/2022
    Screening → FIS Requested

Other projects at this substation