26INR0324 · BESS · Grimes County
Misty Hollow BESS
Misty Hollow BESS is a 246 MW battery storage project in Grimes County, Texas, connecting at 345 kV Singleton (#44645). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0324
- Capacity
- 246 MW
- Fuel
- BESS (BA)
- Substation
- 345 kV Singleton (#44645)
- County
- Grimes County
- Interconnecting entity
- Clear Fork BESS, LLC
- Projected COD
- 07/15/2028
- Entered queue
- 12/06/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/04/2025FIS Approved → IA Signed
- 03/04/2025FIS Requested → FIS Approved
- 12/06/2023Entered the queue with 246 MW, projected COD 07/15/2028
- 12/06/2023Screening → FIS Requested
Other projects at this substation
| Hill Valley BESS | BESS | 246 MW | IA Signed |