Counties / Texas
Coke County power projects
Coke County, Texas has 5 active power projects totalling 808 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 424 MW (52%). The largest single project is Roboman Solar (273 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
0.8 GW capacity
IA signed or later
1
20% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Coke County
COD change
10/01/2026
Ulysses Solar · Solar · Coke County
Projected COD moved 03/02/2027 → 03/17/2027. Delay #1 for this project.
0 mo
Stage change
09/18/2026
Energization Approved
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Roboman Solar | Solar | 273 | Tap 345 kV (#76009) Twin Buttes – (#76090) Divide Ckt 1 | FIS Requested | 07/01/2029 |
| Coke BESS | BESS | 220 | 76090 Divide Switchyard 345kV | FIS Requested | 04/10/2028 |
| Ulysses Solar | Solar | 151 | 60072 Odysseus Substation 345 kV | Energization Approved | 03/17/2027 |
| Hayrick BESS | BESS | 114 | 6351 Nicole 138kV | FIS Approved | 03/15/2028 |
| Fort Chadbourne Cattle BESS | BESS | 50 | 6324 Fort Chadbourne 138 kv | FIS Requested | 06/29/2027 |
For residents and landowners
- What power projects are planned in Coke County?
- ERCOT's October 2026 report lists 5 active projects in Coke County totalling 808 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.