28INR0155 · BESS · Coke County
Coke BESS
Coke BESS is a 220 MW battery storage project in Coke County, Texas, connecting at 76090 Divide Switchyard 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/10/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0155
- Capacity
- 220 MW
- Fuel
- BESS (BA)
- Substation
- 76090 Divide Switchyard 345kV
- County
- Coke County
- Interconnecting entity
- Coke ESS, LLC
- Projected COD
- 04/10/2028
- Entered queue
- 09/27/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/27/2024Entered the queue with 220 MW, projected COD 04/10/2028
- 09/27/2024Screening → FIS Requested