LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0155 · BESS · Coke County

Coke BESS

Coke BESS is a 220 MW battery storage project in Coke County, Texas, connecting at 76090 Divide Switchyard 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/10/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0155
Capacity
220 MW
Fuel
BESS (BA)
Interconnecting entity
Coke ESS, LLC
Projected COD
04/10/2028
Entered queue
09/27/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/27/2024
    Entered the queue with 220 MW, projected COD 04/10/2028
  • 09/27/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.