Substation / point of interconnection ยท Coke County
6324 Fort Chadbourne 138 kv
1 active project totalling 50 MW is queued to connect at 6324 Fort Chadbourne 138 kv in Coke County, Texas, according to ERCOT's October 2026 report.
Active capacity
50 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0218 | Fort Chadbourne Cattle BESS | BESS | 50 | FIS Requested | 06/29/2027 | 0 |