Anderson County power projects
Anderson County, Texas has 9 active power projects totalling 4,645 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 3,789 MW (82%). The largest single project is Mule Deer Run Gas II (1,263 MW natural gas). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
9
4.6 GW capacity
IA signed or later
3
33% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Anderson County
COD change
10/01/2026
Skull Creek Solar · Solar · Anderson County
Projected COD moved 07/30/2027 → 06/30/2027. Moved earlier.
-1 mo
Stage change
09/18/2026
FIS Approved
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Mule Deer Run Gas II | Gas | 1,263 | #3308 Pin Oak 345KV | FIS Requested | 07/01/2032 |
| Mule Deer Run Gas III | Gas | 1,263 | #3308 Pin Oak 345KV | FIS Requested | 07/01/2032 |
| Mule Deer Run Gas | Gas | 1,263 | #3308 Pin Oak 345KV | FIS Requested | 07/01/2031 |
| ALWEST BESS | BESS | 209 | 3114 Paltalco 138kV | FIS Requested | 04/19/2028 |
| Lumen Farm Solar SLF | Solar | 201 | Tap 138kV 3325 Blackburn Switch – 3272 Palestine | FIS Requested | 09/30/2028 |
| Brotherton Storage | BESS | 176 | 6937 Tucker Sub 138kV | IA Signed | 05/01/2027 |
| Skull Creek Solar | Solar | 137 | Tap 138kV 3281 Tennessee Colony - 3499 Blackfoot | IA Signed | 06/30/2027 |
| Pham BESS | BESS | 133 | Tap 138kV 3281 TENNCLNY_8 - 3499 BLACKFTAP_8 | IA Signed | 09/18/2028 |
| Lumen Farm BESS SLF | BESS | 0 | Tap 138kV 3325 Blackburn Switch – 3272 Palestine | FIS Requested | 09/30/2028 |
For residents and landowners
- What power projects are planned in Anderson County?
- ERCOT's October 2026 report lists 9 active projects in Anderson County totalling 4,645 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.