31INR0022 · Gas · Anderson County

Mule Deer Run Gas III

Mule Deer Run Gas III is a 1,263 MW natural gas project in Anderson County, Texas, connecting at #3308 Pin Oak 345KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2032.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
31INR0022
Capacity
1,263 MW
Fuel
Gas (CC)
Interconnecting entity
Anderson Energy Center, LLC
Projected COD
07/01/2032
Entered queue
06/01/2026
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/01/2026
    Entered the queue with 1,263 MW, projected COD 07/01/2032
  • 06/01/2026
    Screening → FIS Requested

Other projects at this substation

Mule Deer Run Gas IIGas1,263 MWFIS Requested
Mule Deer Run GasGas1,263 MWFIS Requested