24INR0450 · BESS · Anderson County
Lumen Farm BESS SLF
Lumen Farm BESS SLF is a 0 MW battery storage project in Anderson County, Texas, connecting at Tap 138kV 3325 Blackburn Switch – 3272 Palestine. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0450
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- County
- Anderson County
- Interconnecting entity
- Neches Solar, LLC
- Projected COD
- 09/30/2028
- Entered queue
- 10/28/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/28/2022Entered the queue with 0 MW, projected COD 09/30/2028
- 10/28/2022Screening → FIS Requested
Other projects at this substation